Reading Time: 7 minutes
An Orlando eminent domain attorney can review an FDOT offer, and the earlier that review starts, the more time you have to respond. FDOT’s fiscal year 2027 through 2031 work program carries about $123.7 million for right-of-way work on 15 Orange County items, and about $65.7 million of it sits in fiscal year 2027.
Which FDOT Projects Are Budgeted to Buy Land in Orange County?
Fifteen items carry right-of-way money, and the eight below carry nearly all of it. FDOT’s adopted work program dated July 1, 2026 counts land purchase, relocation, and related services as right-of-way money. Fiscal year 2027 runs July 1, 2026 through June 30, 2027.
| FDOT item | Corridor | Right-of-way money | Fiscal years |
|---|---|---|---|
| 242484-8 | I-4, east of Osceola Parkway (CR 522) to west of SR 528 | $74.9 million | 2027 to 2029 |
| 446579-1 | Florida’s Turnpike widening, south of SR 408 to north of SR 429 | $21.2 million | 2030 |
| 444980-1 | Florida’s Turnpike at the Taft-Vineland Road interchange | $8.5 million | 2027 |
| 239203-7 | SR 50, east of Old Cheney Highway to Chuluota Road | $6.9 million | 2027 to 2028 |
| 452191-1 | Rail bridge replacement over US 17/92 in Maitland | $6.2 million | 2027 |
| 445696-1 | SR 438 (Silver Star Road) intersection improvements | $2.4 million | 2027 to 2028 |
| 447593-1 | SR 50 (Colonial Drive) at Maguire Boulevard signal rebuild | $1.7 million | 2027 |
| 444979-1 | SR 528 (Beachline) interchange at La Quinta Drive, westbound | $0.9 million | 2027 to 2029 |
A work program year shows when FDOT budgeted the money, not when an offer reaches a particular owner. This table covers FDOT’s adopted program only; other public bodies run separate projects that it does not show.
Is your property on one of these corridors? Talk with a Jimerson Birr eminent domain attorney before FDOT’s appraiser or right-of-way agent contacts you.
I-4 Between Osceola Parkway and SR 528
Item 242484-8 is the largest line in the county, at about $74.9 million for land purchase, relocation, and related services, including $70.2 million for land purchase alone. The item carries no construction phase in the five-year program, and FDOT’s notes on it say right of way is not fully funded. About $51.3 million of its right-of-way money shows as authorized. Our guide to I-4 between Osceola Parkway and SR 528 covers the segment.
Florida’s Turnpike in Orange County
The two largest Turnpike items carry about $29.6 million. Item 446579-1 carries about $21.2 million, all in fiscal year 2030, including $56,574 for relocation. Item 444980-1 pairs about $8.5 million for land with a construction contract of about $55.8 million in fiscal year 2027. Our post on Florida’s Turnpike widening explains what owners along the corridor should expect.
SR 50, Silver Star Road, and Colonial Drive
FDOT’s notes on the Silver Star Road item describe three signalized R-cuts and two signal rebuilds, and say right-of-way corner clips will be needed for strain poles. On a commercial lot, even a small strip can reach access, parking, and other business-critical features.
What Changed From the 2025 Program?
Compared with FDOT’s July 1, 2025 program, no Orange County item with right-of-way money dropped out. One item newly carries right-of-way money: the Maitland bridge replacement, with about $6.2 million for land in fiscal year 2027. Taft-Vineland carried about $30.6 million in fiscal year 2026 in the earlier program, a reminder that programs move every July.
What About Osceola, Seminole, and Lake Counties?
Osceola County carries about $306.0 million across 10 items, led by I-4 from west of CR 532 to Osceola Parkway. See I-4 Beyond the Ultimate and John Young Parkway at Pleasant Hill Road. Seminole County carries about $62.2 million across five items, including the SR 434 roundabouts. Lake County carries about $56.1 million across 11 items, including SR 50 projects. The Wekiva Parkway corridor is shared with Orange County.
Under section 26.021, Orange and Osceola Counties make up the Ninth Judicial Circuit. Under section 73.021 of Chapter 73, Florida Statutes, a condemnation petition may be filed in the circuit court of the county where the property lies. See also our overview of major FDOT projects in Central Florida and eminent domain issues for Orlando commercial property owners.
What Can a Commercial Owner Claim in a Partial Taking?
Section 73.071(3) lists what the jury decides for most commercial owners. Any recovery depends on the facts and evidence.
- The land taken. Its value. Section 73.071(5) excludes value changes that occur after the project’s scope is known in the market and result solely from knowledge of the project location.
- The remainder. Lost value to the land you keep, or severance damages.
- Business damages. Available on a partial right-of-way taking by FDOT or another public body when the taking may damage or destroy an established business of more than five years’ standing, owned by the party whose land is taken and located on adjoining land that party owns or holds. It must be pleaded in written defenses. See business damages under section 73.071.
Tenants can have their own claims, often shaped by the lease’s condemnation clause, so commercial lease review belongs early.
Do you run a business on the land FDOT needs? Request a free consultation before the business damage deadline runs.
What Deadlines Start When FDOT’s Letter Arrives?
Two clocks run from receipt of notice or its return as undeliverable. Under section 73.015, the owner gets at least 30 days to respond to the written offer before FDOT can file suit. In a right-of-way taking, a business owner claiming business damages has 180 days from receipt of the business notice, or a later date both sides agree to, to submit a good faith written offer.
- On request, FDOT must provide the appraisal behind its offer within 15 business days, plus right-of-way maps and construction plans to the extent prepared.
- The business damage offer must include an explanation prepared by the owner, a certified public accountant, or a business damage expert, plus supporting business records, and be sent by certified mail.
- Miss the 180 days without a good faith justification and the court must strike the claim.
- FDOT then has 120 days from receipt of the offer and records to respond. If FDOT does not respond, or rejects the offer without following the statute, the law treats that as a zero-dollar counteroffer when attorney’s fees are later calculated.
If FDOT files under chapter 74, the quick-take process adds its own deadlines.
Who Pays for Your Attorney?
In a condemnation case, the condemning authority pays attorney’s fees under section 73.092 and reasonable costs, including appraisal fees, under section 73.091 of Chapter 73. Fees depend on the result: 33 percent of benefits up to $250,000, 25 percent from $250,000 to $1 million, and 20 percent above that. For most claims, benefits are measured from the last written offer before you hired counsel, or the first written offer after if none came before.
On a road right-of-way taking, section 73.015(4) carries cost and fee recovery into a settlement reached before suit, on the terms it sets out. So it makes sense to talk with a Florida eminent domain attorney before accepting an offer.
Jimerson Birr has an Orlando office and represents Florida property owners in condemnation matters brought by cities, counties, utilities, and state agencies. The work draws on our real estate development, sales, and leasing practice, condemnation attorney services, and easements work. Charles Jimerson’s practice includes eminent domain and easement disputes.
What Should You Check Before You Respond to FDOT?
These facts shape what you can claim:
- The date each notice arrived. The written offer starts the 30-day window; the business notice starts the 180-day clock.
- How much of the property FDOT wants. Driveways, parking, and signs inside the taking line change the remainder.
- How long the business has operated on the site, and who owns it. Business damages need more than five years’ standing and common ownership of land and business.
- Your lease. A condemnation clause can decide how an award is split between landlord and tenant.
- Your site plan approvals. Approved parking, setback, and stormwater numbers show whether the remainder still works.
These facts decide the outcome, and an attorney needs to review them against the appraisal and the plans.
Has FDOT asked to inspect or appraise your property? Talk with a Jimerson Birr eminent domain attorney before you sign a right of entry or respond.
How Can Jimerson Birr Help Orange County Owners Facing FDOT Projects?
If FDOT projects in Orange County need part of your land, Jimerson Birr can request and review the state’s appraisal and plans, work with real estate appraisers, and pursue remainder and business damages through our Florida eminent domain practice. Call (904) 389-0050 or request a free consultation. Waiting has a cost: FDOT may file suit once the 30 days after you receive its notice pass, and a business damage claim must be struck if the offer is late, absent a good faith justification.